Expert site inspection to be carried out on October 8 in the Varto geothermal project case
The Bingöl Administrative Court ordered an expert‑led inspection for the geothermal drilling project in Çaylar village, Varto, to take place on 8 October 2026.
In its decision dated 23 September 2026, the Bingöl Administrative Court ordered an expert‑led inspection for the geothermal resource exploration project planned within the boundaries of Çaylar (Xwarik) village in the Varto district of Muş. The inspection will be carried out on 8 October 2026 at 10:00 a.m., and the court panel will travel to the site at 08:30 that same day.
The project is being carried out by IGNIS H2 Energy Production Inc., a U.S.-based company, which has obtained a work permit from the Provincial Commission of the Muş Governorship. The Varto Ecology Platform and the surrounding villages, represented in the lawsuit by lawyer Barış Yıldırım, have asked for the project to be halted, seeking the reversal of the “Environmental Impact Assessment Not Required” decision and the suspension of the works.
The petition states that the project area serves as habitat for protected species such as the wild goat, the chamois with hooked horns, and the lynx, and that agriculture, livestock breeding and beekeeping are also practiced there. It points to the possible impacts of geothermal drilling on groundwater and surface water, as well as the presence of archaeological sites and immovable cultural heritage in the region. The court asked the expert panel to assess the potential effects on the environment, ecology, biodiversity, underground water resources, agriculture, forest lands and protected species, and to examine the adequacy of the project dossier and whether an Environmental Impact Assessment report is required.
After the expert examination and site inspection are completed, the resulting report will be served on the parties, any objections will be considered, and the request to halt the works will be decided upon after that process.